Traced mini-case
Midlands 220 kV uprate sample
This case acts as a mid-range reference where statutory progress is visible, but public reporting still requires judgment to separate planning from permitting.
14 Feb 2022 to 18 Dec 2025
Every milestone shown on this page feeds the case reconstruction.
Each dated step is tied back to at least one public source reference.
The same stage model is used to anchor the dashboard-level timing statistics.
- Planning
14 Feb 2022
Programme enters formal planning scope
Used as the first comparable anchor because the project enters the operator's formal development stack at this point.
- Permitting
3 Nov 2022
Primary statutory consent package filed
Public programme update marks the transition from preparatory planning work into formal consent handling.
- Permitting
26 Apr 2024
Primary approval decision published
Used as the permitting end point because it is the clearest public sign that the project can move into executable delivery.
- Appealing
12 Jun 2024
Appeal and review window closes
A short appeal allowance is retained even though reporting does not disclose a lengthy contested process.
- Build
18 Dec 2025
Commissioning or energisation signalled
Used as the traced delivery end point because public reporting shifts from project approval to operational readiness.